Completion of high school project delayed another year

Completion of high school project delayed another year

Source: AXA XL Environmental

To achieve the completion date on a school project, the GC accelerated its schedule, allowing the drywall contractor to start before the building envelope was completed. Rain damaged a majority of the installed drywall as well as the materials stored on site. This resulted in $2 million in repair costs and associated delay costs, borne by the GC.