Tampa Bay Water, reservoir engineer reach settlement

Source: Tampa Bay Online, February 21, 2011

The region’s water supplier settled today with the general contractor of its faulty reservoir but will continue to pursue a lawsuit against the engineering company that designed the 15-billion gallon structure.

The settlement approved by Tampa Bay Water’s board calls for contractor Barnard Construction and subcontractor McDonald Construction Corp. to pay $750,000 before the case goes to trial. The company also could be liable for up to $5 million, depending on the outcome of the case.

Tampa Bay Water will continue its case against HDR Engineering, the company that designed the massive, above-ground reservoir in southeastern Hillsborough County.

The regional utility is suing to recover some of the $125 million estimated cost to fix cracks in the soil cement covering over the sides and bottom of the reservoir. The reservoir cost $140 million to build.…